By Charlotte McCoy, Director of Schools for Campbell County
JACKSBORO, TN (SPECIAL TO WLAF)- In April 2026, I accepted the position of Director of Campbell County Public Schools with a commitment to transparency, open communication, and keeping our community informed. I believe our students, families, staff, and taxpayers deserve clear and accurate information about matters that affect our schools. For that reason, I want to provide an update regarding the Jacksboro Elementary School construction project.
TOP PHOTO: DOS Charlotte McCoy
GCE Construction, LaFollette, Tn entered into a contract with the Campbell County Board of Education on May 20, 2024, for renovations and additions to Jacksboro Elementary School. The contract amount is $2,490,000, with the project originally anticipated to be completed in time for the fall 2025/2026 school year. The Lewis Group Architects, Inc. was retained to provide architectural and project-related services.

Current Status of the Project
When I became Director of Schools in April 2026, the project remained unfinished and was already behind the anticipated schedule. Since that time, the Board and school administration have continued working to understand the remaining issues and determine what is necessary to bring the project to completion.
Several construction items remain under review. These include observed issues involving portions of the cafeteria tile flooring, variations in exterior grout color, and a gap between a door and its threshold. These items remain under review and are subject to resolution through the applicable project closeout process. One of the Board's most significant concerns is the gymnasium floor, which currently has a visible buckle. Preliminary estimates available to the Board indicate that replacement could cost approximately $140,000.
These issues are important to the Board not simply because they involve construction, but because they affect our students. Our students deserve safe, functional, and properly completed spaces in which to learn, eat, play, and participate in school activities. Our goal is to have these facilities completed and available for their intended use as soon as reasonably possible.
How Construction Payments Are Processed
I also want to clarify the process the Campbell County Board of Education follows when making payments on a construction project. Public school districts typically use an architect or engineer as a third-party professional to review construction work and payment requests. For this project, The Lewis Group Architects, Inc. serves in that professional role.
GCE Construction submits a detailed payment application identifying the work and materials it says have been completed and the amount it is requesting to be paid. The payment application is based on the agreed-upon breakdown of the project's costs.
The Lewis Group Architects, Inc. reviews payment applications in accordance with its contractual responsibilities and provides its applicable review, certification, or recommendation regarding payment. The payment application is then considered by the Campbell County Board of Education in accordance with the applicable contract requirements and approval procedures.
As of October 8, 2026, The Lewis Group Architects, Inc. has reviewed and recommended approval of Pay Applications Nos. 1 through 9. The Board's records reflect that those applications were approved and paid in accordance with the applicable procedures. It is important for the public to understand that the Board does not independently determine the amount of construction work that has been completed or simply approve a contractor's requested amount without the required review. The architectural review is an important part of the process designed to protect the school system and the taxpayers.
Moving Forward
Throughout this project, the Board has attempted to work with GCE Construction. The Board's objective has remained consistent: to see the work completed properly so that our students and community can use the facilities for which this project was undertaken.
I also recognize that there have been questions and differing statements about the project on social media and other platforms. I will not respond to every statement or post. Instead, I will continue to provide the community with information about the project when appropriate and when doing so does not interfere with ongoing discussions or legal processes.
At the end of the day, this project is more than a construction contract. It is about our children. Our students deserve school facilities that are safe, functional, properly completed, and available for their intended use. We remain committed to working toward that goal. The Campbell County Board of Education and I remain committed to doing everything within our authority to move this project toward completion and to protecting the interests of our students, families, staff, and taxpayers.
Thank you for your continued support of Campbell County Public Schools and, most importantly, our children.
Charlotte McCoy
Director of Schools
Campbell County Board of Education